Annual Town Meeting 2024: Warrant Article 13

Union School Building Restoration and Rehabilitation
important update
Article 13 requests a total of $1,132,750 - $200,000 from CPA Historic Preservation Allocation and to borrow the remaining balance of $932,150 - to rehabilitate and restore the exterior of the Union School Building. This request is derived from an update of the original condition assessment performed by Spencer Preservation Group, and also includes a 15% contingency.
Over the last year, the Union Building Rehabilitation Committee has worked with Northern Middlesex Council of Governments and Spencer Preservation Group to identify potential and viable re-use options and a plan to improve the building which has included an extensive community outreach program. As a result of this work, a Final Project Report will narrow down re-use options for the community to consider.
You can find more information on all Town Meeting articles at dunstable-ma.gov/atm2024